Key takeaways
- Work out the labor for lime render over old masonry repairs, from surface preparation and mixing to floating, drying, setting time, curing and the second coat.
As an Amazon Associate I earn from qualifying purchases. This post may contain affiliate links at no extra cost to you.
Lime render over old masonry repairs is slow work, and the slowness is the point. The wall has to be read, the loose material has to come off, the repairs have to be made good, and each coat has to set in its own time before the next one goes on. A worker who prices the job by the square metre alone will run out of time halfway through, because the time is not in the square metres. It is in the preparation, the waiting, and the second coat. how to estimate labor when you apply lime render over compatible old masonry repairs is a question about counting the whole job, not just the hours the trowel is in the hand.
The labor on a lime render job falls into five blocks. Preparation takes the longest share on an old wall: reading the surface, removing loose material, dealing with salt, and making good the joints. Mixing and laying on is the most visible block, and the one most people count first, but it is rarely more than a third of the total. Floating and finishing is the skilled block, and it cannot be rushed without spoiling the coat. Waiting time sits between the coats, and it has to be planned as work, not as a gap, because the wall has to be kept damp and covered while it sets. Cleaning and protection is the last block, and it is the one most often forgotten, which is why tools get ruined and finishes get marked on the last day.
This guide works through each block in order, with the time each one takes on a typical wall, the materials that set the pace, and the way the blocks add up into a full estimate. It uses six materials that suit old masonry repairs, with the verified facts for each one. After the materials come the working steps, the mistakes that blow the estimate apart, and answers to the questions that come up most often when a job is priced. Nothing here gives a money figure, because the figure changes with the place and the season, and the guide is about time, which is the part of the job the worker controls.
Tools and materials
Kerakoll Biocalce Intonaco
- WTA-certified plaster based on NHL 3.5 natural hydraulic lime
- Consumption about 1.3 kg per square metre per mm of thickness
- Supplied in 25 kg bags
- Mixing about 5.1 litres of water per 25 kg bag
- See product page for full application notes
Kerakoll Biocalce Intonaco is the lead render for old masonry repairs because its consumption figure lets the worker count the material and the labor in the same pass. At about 1.3 kg per square metre per millimetre of thickness, a coat of known thickness over a wall of known area gives a firm number of bags, and the number of bags gives the number of mixes, and the number of mixes gives the hours. The NHL 3.5 base sets with water as well as with air, which matters on old masonry where the lower courses stay damp and a purely air-setting coat would stay soft. The WTA certification means the plaster has been checked for use on damp masonry, which is the background most old repairs present. Mix each bag with about 5.1 litres of clean water, keep the mix the same for every batch, and lay the coat on at the thickness the wall needs rather than the thickness the bucket allows.
Kerakoll Biocalce Intonaco Fino
- Plaster based on NHL 3.5 natural hydraulic lime, finer grade body coat
- Consumption about 1.2 kg per square metre per mm of thickness
- Supplied in 25 kg bags
- Mixing about 5.1 litres of water per 25 kg bag
- Application temperature plus 5 C to plus 35 C
Kerakoll Biocalce Intonaco Fino is the finer grade body coat, and it sets the pace of the second coat on an old masonry repair. The finer aggregate lays smoother and floats faster than the coarser grade, which saves time on the finish, but it also shows every trowel mark, so the floating has to be done well. The consumption of about 1.2 kg per square metre per millimetre lets the worker count the second coat in the same way as the first, and the temperature range of plus 5 C to plus 35 C sets the working window for the day. Below plus 5 C the coat will not set, and above plus 35 C it will dry too fast and craze. Plan the second coat for the middle of the day in cold weather and for the morning in hot weather, and keep the wall damp while the coat is worked.
Mike Wye Lime Plaster 2/1
- Traditional premixed lime plaster from selected sands and mature lime putty
- Matured for several weeks before supply
- Ratio 2 parts sand to 1 part mature lime putty by volume
- For final coat internal skimming
- See product page for full application notes
Mike Wye Lime Plaster 2/1 is the premixed plaster for the finish coat where the repair needs a traditional lime surface, and its value in an estimate is that it removes the mixing time from the job. The plaster arrives matured for several weeks, so the worker does not spend the morning gauging sand and putty, and the ratio of two parts sand to one part putty is fixed, so every batch behaves the same. That consistency saves time on the wall, because a mix that changes from batch to batch dries at different rates and leaves a patchy finish that has to be corrected. Use this plaster where the finish needs to match an old lime surface, and keep the coats thin, because a premixed lime plaster laid on thick will shrink as it dries and crack across the face.
Mike Wye Lime Putty
- High calcium lime putty slaked and matured for a minimum of three months
- Sand 0 to 1 mm
- Lime to BS EN 459-1
- 99.99 per cent finer than 0.18 mm particle size
- See product page for pack sizes
Mike Wye Lime Putty is the binder for the repairs that come before the render, and it belongs in the estimate because the repair time is the part most often left out. Putty slaked and matured for at least three months is smooth and fatty, so it fills joints and small holes without shrinking back, and the fine particle size means it works into the surface cleanly. The putty is used to re-point the joints where the old mortar has fallen away and to fill the small defects that would otherwise show through the render. Each repair takes minutes, but a wall with a hundred repairs takes a day, and that day has to be in the estimate. Leave the repairs to firm up before the render goes on, because a render coat laid over soft putty will dry darker over the repair.
Washed sharp sand
- Clean well-graded sharp sand
- Typical base coat ratio 1 part lime to 2.5 to 3 parts sharp sand by volume
- See product page for bag sizes
Washed sharp sand is the aggregate that sets the thickness and the working time of the base coat, and it matters in an estimate because the ratio decides how far a bag of lime goes. A base coat mixed at one part lime to two and a half to three parts sharp sand by volume gives a coat that keys well into old masonry and holds its thickness without slumping. Clean sand is essential, because sand with clay or silt in it will weaken the coat and slow the set, and the time lost to a failed coat is far greater than the time saved by using dirty sand. Count the sand in the same pass as the lime, bag by bag, and keep the ratio the same for every mix so the coat dries at one rate across the wall.
Chopped horsehair
- Natural fibre reinforcement for base coat lime plaster
- About 2 to 3 kg per cubic metre of mix
- See product page for pack sizes
Chopped horsehair is the fibre that holds a thick base coat together on old masonry, and it saves labor by letting the worker lay the coat on in one pass instead of two. At about 2 to 3 kg per cubic metre of mix, the fibre spreads through the render and ties it together as it dries, which stops the coat from cracking as it shrinks. On a wall with deep joints and uneven brick, a fibre-reinforced base coat can be laid thicker in one pass, and that removes a whole day of waiting for a second coat. Mix the fibre in evenly, teasing out any clumps before the mix goes on the wall, because a clump of fibre in the coat will show as a lump in the finish and has to be picked out by hand.
| Item | Key spec | Best for |
|---|---|---|
| Kerakoll Biocalce Intonaco | NHL 3.5 base; 1.3 kg per sq m per mm; 25 kg bags | Counting the base coat by bags and mixes |
| Kerakoll Biocalce Intonaco Fino | Finer grade; 1.2 kg per sq m per mm; 5 to 35 C | Second coat that floats fast and smooth |
| Mike Wye Lime Plaster 2/1 | Premixed; 2 parts sand to 1 part putty | Finish coat with no gauging time |
| Mike Wye Lime Putty | Matured 3 months; 99.99 per cent finer than 0.18 mm | Re-pointing joints and small repairs |
| Washed sharp sand | Base coat ratio 1 part lime to 2.5 to 3 parts sand | Setting base coat thickness and working time |
| Chopped horsehair | 2 to 3 kg per cubic metre of mix | Thick base coats in one pass |
Step by step
Step 1: Measure the wall and count the repairs
Measure the wall in square metres, bay by bay, and note the height, because a high wall takes longer than a low one of the same area. Count the repairs: the joints that need re-pointing, the holes that need filling, the loose bricks that need resetting, and the areas where the old render has to come off. A wall with a hundred small repairs takes a full day of preparation, and a wall with ten takes an hour, and the estimate has to show the difference. Note the access as well. A wall that needs a scaffold takes longer than one reached from the ground, and a wall behind a hedge takes longer than one with a clear run. Write the count down, bay by bay, so the estimate can be checked against the wall when the work starts.
Step 2: Count the material from the consumption figures
Work out the material from the consumption figures, coat by coat. A base coat of Kerakoll Biocalce Intonaco at about 1.3 kg per square metre per millimetre, over a wall of known area and a thickness the wall needs, gives a firm number of 25 kg bags. A second coat of Intonaco Fino at about 1.2 kg per square metre per millimetre gives a second number. Add the sand at the ratio of one part lime to two and a half to three parts sand, and the horsehair at 2 to 3 kg per cubic metre of mix. The material count gives the labor count, because every bag is a mix, and every mix is time at the mixer and time carrying the mix to the wall. Allow a margin for waste, because a wall with deep joints takes more material than a flat one, and a margin for the small patch that has to be laid to check the bond before the full coat.
Step 3: Allow the preparation time in full
Preparation is the longest block on an old wall, and it is the one most often cut short. Removing loose material, brushing the surface back to a firm edge, dealing with salt, and re-pointing the joints with lime putty all take time, and none of it can be skipped without the render failing. Allow a full day of preparation for a wall that is in poor condition, and half a day for one that is sound. The putty repairs need time to firm up before the render goes on, so the preparation day and the render day are separate days, and the estimate has to show them as separate days. A worker who tries to repair and render on the same day will lay the render over soft putty, and the render will dry darker over every repair.
Step 4: Allow the mixing and laying-on time
Mixing and laying on is the most visible block, and the one most people count first. A mixer and a labourer can keep a plasterer supplied on a straightforward wall, but on a wall with deep joints and uneven brick the laying on is slower, because the coat has to be pressed into the joints and ruled to thickness. Allow the time for the mix to be gauged the same for every batch, because a mix that changes from batch to batch dries at different rates and leaves a patchy finish. Count the mixes from the material count, and count the carrying time from the distance between the mixer and the wall. A mixer set far from the wall adds an hour a day in carrying, and that hour has to be in the estimate.
Step 5: Allow the floating and finishing time
Floating and finishing is the skilled block, and it cannot be rushed. The coat has to firm up before it is floated, and the floating has to be done well, because a coat floated too soon tears and a coat floated too late will not close. Allow the time for the coat to firm up, and allow the time for the floating itself, which is slower on a wavy wall than on a flat one. The finish coat takes longer still, because it has to be laid thin and floated to a smooth, even surface. A worker who rushes the finish will leave trowel marks that show in raking light, and the time to correct them is longer than the time to do the job well in the first place.
Step 6: Plan the waiting time between coats
Waiting time sits between the coats, and it has to be planned as work, not as a gap. The first coat needs time to set before the second goes on, and the wall has to be kept damp and covered while it sets. In warm weather the coat needs misting, and in cold weather it needs covering, and both take time. Plan the coats so the waiting time falls overnight where possible, with the first coat laid in the afternoon and the second in the morning. Where the job is small, the waiting time can mean a day with no trowel work, and that day still has to be in the estimate, because the worker is on site keeping the wall damp and covered. A job priced without waiting time will run over, because the coats cannot be rushed.
Step 7: Add the cleaning, protection and snagging time
Cleaning and protection is the last block, and it is the one most often forgotten. The tools have to be cleaned between coats and at the end of the day, the floor has to be covered and cleared, and the finished render has to be protected from rain and sun while it sets. Allow the time for the hessian to be hung and taken down, for the mixer to be washed out, and for the trowels to be cleaned and dried. Then allow the snagging time: a visit after a day to look at the wall in raking light, note where the coat is thin or the colour is uneven, and make good the small defects. A job without snagging time is a job that leaves the small defects in place, and the wall will show them for years.
Common mistakes
Pricing by the square metre alone
A square metre of sound wall and a square metre of wall with a hundred repairs are not the same job, and a price that counts them the same will run out of time halfway through. Count the repairs, count the access, and count the preparation as a separate block. The square metres only tell the worker how much material to order.
Leaving the preparation time out of the estimate
Preparation is the longest block on an old wall, and leaving it out is the fastest way to lose a day. Removing loose material, dealing with salt, and re-pointing the joints all take time, and none of it can be skipped. Allow the preparation in full, and show it as a separate day where the wall is in poor condition.
Forgetting the waiting time between coats
Lime render sets slowly, and the coats cannot be rushed. A job priced without waiting time will run over, because the worker is on site keeping the wall damp and covered while the coats set. Plan the coats so the waiting falls overnight where possible, and show the waiting as work in the estimate.
Mixing different batches at different ratios
A mix that changes from batch to batch dries at different rates and leaves a patchy finish that has to be corrected. Keep the ratio the same for every batch, count the mixes from the material count, and allow the time to gauge each batch properly. The time saved by rushing the mix is lost twice over in corrections.
Rushing the floating to save time
A coat floated too soon tears, and a coat floated too late will not close. The floating has to be done when the coat is firm, and it has to be done well. A worker who rushes the finish will leave trowel marks that show in raking light, and the time to correct them is longer than the time to do the job well.
FAQ
How long does preparation take on an old masonry wall?
It depends on the condition. A sound wall takes half a day to read, clean and make good. A wall in poor condition, with loose material, salt and a hundred joints to re-point, takes a full day or more. Count the repairs bay by bay before pricing, and show the preparation as a separate block in the estimate.
How do I count the material for a lime render job?
Use the consumption figures. A base coat of Kerakoll Biocalce Intonaco at about 1.3 kg per square metre per millimetre, over a wall of known area and thickness, gives the number of 25 kg bags. Add the sand at the ratio of one part lime to two and a half to three parts sand, and the horsehair at 2 to 3 kg per cubic metre. Allow a margin for waste on a wall with deep joints.
Can the first and second coats go on the same day?
No. The first coat needs time to set before the second goes on, and the wall has to be kept damp and covered while it sets. Plan the coats so the waiting falls overnight, with the first coat in the afternoon and the second in the morning. Rushing the coats will leave a weak bond and a patchy finish.
What slows a lime render job down most?
Preparation on a wall in poor condition, and waiting time between coats. Both are fixed by the wall and the material, not by the worker, and both have to be in the estimate. Access is the third factor: a wall that needs a scaffold or a long carry from the mixer takes longer than one reached from the ground.
Should I allow snagging time in the estimate?
Yes. Allow a visit after a day to look at the wall in raking light, note where the coat is thin or the colour is uneven, and make good the small defects. A job without snagging time leaves the small defects in place, and the wall will show them for years.
Conclusion
Estimating labor for lime render over old masonry repairs is a job of counting the whole job, not just the hours the trowel is in the hand. Preparation takes the longest share on an old wall, mixing and laying on follows the material count, floating and finishing is the skilled block that cannot be rushed, waiting time sits between the coats, and cleaning and protection closes the job. Kerakoll Biocalce Intonaco and Intonaco Fino give the consumption figures that turn square metres into bags and bags into mixes, Mike Wye Lime Plaster 2/1 removes the gauging time from the finish, and lime putty, sharp sand and horsehair set the pace of the repairs and the base coat. Count the repairs bay by bay, count the material coat by coat, allow the waiting time in full, and show the snagging as work. Done this way, the estimate will hold, the coats will set in their own time, and the wall will carry a render that lasts.
Related guides
More ways to save on your next finish
Programs that pair well with the guide above. Offers and eligibility are set by Amazon and may change.
A free business account with business pricing and bulk-buying tools for work, shop or home office.
Create a business accountFast, free shipping on eligible items, plus Prime Video and more. Eligible new members can start with a free trial.
Start a Prime free trialRead from a huge library of eBooks, including how-to guides and cookbooks. Eligible new members can start with a free trial.
Try Kindle UnlimitedAudiobooks and podcasts for the commute, the garage or the kitchen. Eligible new members can start with a free trial.
Try Audible freeAs an Amazon Associate we earn from qualifying purchases. Using these links costs you nothing extra.
Write Your Review
No reviews yet. Be the first to share your experience!